Plant capacity refers to how much material your plant can process in one hour, measured in tonnes per hour (TPH). For example, if your plant can handle 10 tonnes of material in an hour, its capacity is 10 TPH. This number is critical because it directly affects how fast you can complete your projects and how much you can supply to the market.
Let’s break down how to calculate the right TPH for your plant.
Step 1: Know Your Market Demand
Start by estimating how much material you’ll need to process in a year. This depends on the size of your projects or how much material you’ll supply to others.
Ask Yourself:
How much material will my projects need in total? (e.g., tonnes per year)
Are there times when demand is higher, like during the construction season?
Example:
If your projects need 50,000 tonnes of aggregates in a year, this is your starting point.
Step 2: Decide How Long Your Plant Will Run
No plant operates 24/7. You need to account for maintenance, holidays, and other downtimes.
Steps to Calculate Operating Time:
Decide how many days per year your plant will run (e.g., 300 days).
Decide how many hours per day it will operate (e.g., 16 hours).
Formula:
default Operating Hours Per Year = Days Per Year × Hours Per Day
Example: If your plant runs 300 days a year for 16 hours daily:
default Operating Hours Per Year = 300 × 16 = 4,800 hours/year
Step 3: Calculate the Tonnes Per Hour (TPH)
Once you know your yearly demand and how many hours your plant will run, you can calculate the required TPH.
Formula:
default Required TPH = Annual Demand ÷ Operating Hours Per Year
Example:
If your annual demand is 50,000 tonnes and you have 4,800 operating hours:
default Required TPH = 50,000 ÷ 4,800 = 10.42 TPH
This means your plant should process at least 10.42 tonnes every hour.
Step 4: Plan for Future Growth
Construction demand in India is growing rapidly, so your plant needs to handle future increases in demand. Add a buffer to your capacity to ensure you’re ready for growth.
Adjusted TPH Formula:
default Adjusted TPH = Required TPH × (1 + Growth Rate)
Example:
If you expect a 20% increase in demand:
default Adjusted TPH = 10.42 × (1 + 0.2) = 12.5 TPH
In this case, you should plan for a plant with a capacity of around 12.5 TPH.
Step 5: Think About Practical Issues
Even after calculating your TPH, check these factors:
Material Type: Can the plant handle different materials like basalt, quartz, or limestone?
Raw Material Supply: Will you always have enough materials to keep the plant running?
Budget: Higher capacity plants may cost more initially but can save money in the long run.
Why Choosing the Right Capacity is Important
Getting your plant capacity right means:
Faster Work: Avoid delays due to underpowered equipment.
Cost Efficiency: Avoid overpaying for equipment you don’t fully use.
Future Readiness: Be prepared for more demand without expensive upgrades.
Real-Life Example:
Let’s say you’re setting up a plant for road construction. Your annual demand is 75,000 tonnes, and you plan to run the plant 10 hours a day for 300 days a year. If you expect a 15% growth buffer:
Base TPH:
default Required TPH = 75,000 ÷ (300 × 10) = 25 TPH
Adjusted TPH:
default Adjusted TPH = 25 × (1 + 0.15) = 28.75 TPH
For this project, you should plan for a capacity of around 30 TPH.
Final Thoughts
Whether you’re crushing limestone for a cement plant, breaking bricks for aggregates, or processing basalt for a dam, getting the right plant capacity is critical. By following these simple steps, you can make sure your plant is cost-effective, efficient, and ready for future growth.